How Much Concrete Do I Need? (Slabs, Paths and Post Holes)
How to work out the concrete for a slab, path, shed pad or a row of post holes, and whether to buy bags or ready-mix.
Concrete is sold by the cubic metre (m³), or in bags that each make a small part of one. Work out the volume, add some for waste, and convert it to what you're buying.
1. Slabs, paths and pads
Volume (m³) = length (m) × width (m) × thickness (m).
- The thickness is usually given in millimetres, so divide by 1,000. For example, 100 mm is 0.1 m.
- If the ground isn't level, use the average thickness.
- The thickness itself should come from the plans or the shed maker's slab detail, not from a guess.
Example: a 3 m × 3 m pad, 100 mm thick: 3 × 3 × 0.1 = 0.9 m³.
2. Round post holes
Each hole is a cylinder: π × radius² × depth. Take off the space the post itself fills.
Concrete per hole = (π × (diameter ÷ 2)² × depth) − (post width² × depth).
Example: 10 holes, 300 mm across and 600 mm deep, each holding a 100 mm square post.
- Hole: π × 0.15² × 0.6 = about 0.0424 m³.
- Post: 0.1 × 0.1 × 0.6 = 0.006 m³.
- Concrete per hole: about 0.0364 m³.
- 10 holes: about 0.36 m³.
Set the post size to 0 for a solid footing with no post in it.
3. Add waste
Uneven ground, spillage and overfill always use more than the sum. The calculator adds 10% as a starting point.
- Slab: 0.9 × 1.1 = 0.99 m³.
- Post holes: 0.364 × 1.1 = about 0.40 m³.
4. Bags or ready-mix?
Premix bags. Many 20 kg premix bags make about 0.01 m³ each, but yields vary by brand and bag size, so check the bag.
- Slab: 0.99 m³ ÷ 0.01 = about 100 bags, which is about 2 tonnes to carry and mix.
- Post holes: 0.40 m³ ÷ 0.01 = about 41 bags.
Ready-mix. Suppliers sell by the cubic metre and may have minimum loads or short-load fees. For a slab that's about a cubic metre or more, ring a supplier and compare before you buy 100 bags.
5. Before you pour
- Approvals. Check with your council whether the slab or shed needs approval.
- Before You Dig. Contact Before You Dig Australia (1100.com.au) before digging holes or footings.
- Safety. Wet cement and concrete can burn skin and eyes. Wear gloves, eye protection and long sleeves, and follow the safety information on the bag.
- Design. This guide works out the volume only. It isn't a slab or footing design. Reinforcement, footing size and concrete strength should come from the plans, the shed or building maker, or an engineer.
6. Common mistakes
- Forgetting to convert millimetres to metres.
- Leaving out waste.
- Not taking the post's own volume off each hole (the calculator does it for you).
- Buying bags for a job big enough for ready-mix.
- Guessing slab thickness instead of using the maker's detail.
7. Quick summary
- Slab volume = length × width × thickness (in metres).
- Post hole = π × r² × depth, minus the post.
- Add about 10% for waste.
- Check the bag's yield, or price ready-mix for bigger jobs.
- Call Before You Dig, check approvals, and protect your skin and eyes.
Try it with your own job: Concrete & Area Calculator.
General information only. Follow the plans, the maker's instructions and the safety information on the bag.