How Much Concrete Do I Need? (Slabs, Paths and Post Holes)

How to work out the concrete for a slab, path, shed pad or a row of post holes, and whether to buy bags or ready-mix.

← Farm & Yard guides

Concrete is sold by the cubic metre (m³), or in bags that each make a small part of one. Work out the volume, add some for waste, and convert it to what you're buying.

1. Slabs, paths and pads

Volume (m³) = length (m) × width (m) × thickness (m).

Example: a 3 m × 3 m pad, 100 mm thick: 3 × 3 × 0.1 = 0.9 m³.

2. Round post holes

Each hole is a cylinder: π × radius² × depth. Take off the space the post itself fills.

Concrete per hole = (π × (diameter ÷ 2)² × depth) − (post width² × depth).

Example: 10 holes, 300 mm across and 600 mm deep, each holding a 100 mm square post.

Set the post size to 0 for a solid footing with no post in it.

3. Add waste

Uneven ground, spillage and overfill always use more than the sum. The calculator adds 10% as a starting point.

4. Bags or ready-mix?

Premix bags. Many 20 kg premix bags make about 0.01 m³ each, but yields vary by brand and bag size, so check the bag.

Ready-mix. Suppliers sell by the cubic metre and may have minimum loads or short-load fees. For a slab that's about a cubic metre or more, ring a supplier and compare before you buy 100 bags.

5. Before you pour

6. Common mistakes

7. Quick summary

Try it with your own job: Concrete & Area Calculator.

General information only. Follow the plans, the maker's instructions and the safety information on the bag.

↑